Steel supports and scaffolding often arrive on the same truck and get stored in the same yard, which encourages the assumption that they are interchangeable. They are not. One is designed to carry vertical load from wet concrete; the other is designed to give people a safe place to stand and work.

Using the wrong one is usually not dramatic immediately, which is part of the problem. A support pressed into service as access, or scaffolding loaded as shoring, will often appear to work right up to the point where it does not.
Different Jobs, Different Load Cases
A steel support is a compression member. It carries the weight of wet concrete, formwork, reinforcement and construction live load down to a bearing surface, and it is specified by extension range and load class at that extension.
Scaffolding is an access structure. Its design load is dominated by operatives, tools and stored materials distributed across platforms, and its stability comes from ties to the permanent structure and from its bracing pattern. Both are temporary, but they are not solving the same problem.
When Shoring Is the Correct Answer
Anything that has to hold wet concrete in position is shoring work: slabs, beams, drop panels, transfer structures and any temporary propping during alteration of an existing building. Steel supports, bottom supports and head jacks are the right tools here, sized by calculation rather than availability.
Formwork support also has a sequence dimension. Props stay in place until the concrete has gained sufficient strength, which means the equipment is occupied for days or weeks, and removal is governed by the concrete rather than by the programme.
When Access Is the Correct Answer
Façade work, cladding, painting, inspection, and any task where the requirement is a safe working platform at height is scaffolding work. The governing considerations are platform width, loading class, tie pattern and edge protection, not the compression capacity of individual members.
Where a scaffold also has to carry material storage or support formwork, that is a different design case and has to be treated as one. Assuming a standard access scaffold can absorb shoring loads is a common and expensive mistake.
The Grey Areas Worth Designing
Some situations genuinely sit between the two: shoring towers built from scaffold components, support scaffolding under heavy plant, and temporary propping of an existing structure during demolition of an adjoining element.
In these cases the load path is less predictable than in either pure case, and the correct response is a temporary works design rather than a choice from the store. A component rated for one duty does not acquire capacity in another by being used carefully.
Practical Consequences of Mixing Them
Mixing the two systems produces familiar site problems: props used as platform supports without lateral restraint, scaffold tubes used as shoring without any rating, and base jacks borrowed between systems with mismatched diameters.
Each of these creates eccentricity or removes restraint. The discipline that prevents them is simple: specify by duty, keep the fleets separate in the yard, and treat any crossover as a design question rather than a stores question.